How we build

Nine stages from the first site visit to handing over the keys. At the end of each stage you get dated photos and the engineer's record, and only then is that stage's payment due.

  1. Site visit and soil check1 to 2 weeks

    Our engineer walks the plot with you and checks levels, soil, drainage and access for lorries.

    You receive: Site notes with photos, and a written estimate itemised floor by floor.

    No payment at this stage

  2. Agreement and drawings2 to 4 weeks

    Drawings and the structural design are finalised. The contract lists every specification, the stage payments and the handover date.

    You receive: The signed contract, drawings and a week-by-week schedule.

    10%of the contract is paid at the end of this stage; 10% paid by then

  3. Foundation and plinth4 to 6 weeks

    Excavation, footings, laterite foundation and the plinth beam, with anti-termite treatment.

    You receive: Dated photos of every footing before it is covered, and the engineer's level check.

    15%of the contract is paid at the end of this stage; 25% paid by then

  4. Ground-floor walls and slab6 to 8 weeks

    Columns, block walls and the ground-floor roof slab, cast in one pour.

    You receive: The pour record: concrete grade, cube test results, and photos of the steel before casting.

    20%of the contract is paid at the end of this stage; 45% paid by then

  5. First-floor walls and slab6 to 8 weeks

    The same again for the upper floor.

    You receive: The pour record and cube test results for the second slab.

    20%of the contract is paid at the end of this stage; 65% paid by then

  6. Roof3 to 4 weeks

    Steel or timber roof frame and clay tiles; waterproofing on any flat areas.

    You receive: Photos of the frame and flashing before the tiles go on.

    10%of the contract is paid at the end of this stage; 75% paid by then

  7. Plaster, wiring and plumbing6 to 8 weeks

    Concealed wiring and plumbing are laid and pressure-tested before plastering covers them.

    You receive: The pressure-test record and the wiring layout drawing.

    10%of the contract is paid at the end of this stage; 85% paid by then

  8. Flooring, doors and finishes6 to 10 weeks

    Floors, doors, windows, painting, fittings and fixtures.

    You receive: Photos of each room, and the brands and batch numbers of tiles and paint.

    10%of the contract is paid at the end of this stage; 95% paid by then

  9. Handover1 week

    A joint inspection with you; every item on the snag list is closed before the keys are handed over.

    You receive: As-built drawings, warranty cards and completion photos.

    5%of the contract is paid at the end of this stage; 100% paid by then

In every contract

Defect liability, 12 months
Any defect in our work found within 12 months of handover is repaired free, within 14 days of being reported.
Structure, 10 years
Columns, beams and slabs are warranted for 10 years against structural defects in our work.
Leaks, 5 years
Roof and bathroom leaks within 5 years of handover are repaired free.
Site visits
You can visit the site on any working day. The engineer is there at every slab pour.
Late handover
If we hand over late for reasons in our control, we pay ₹1,000 for each week of delay, up to 2% of the contract.